Road Transport and Bridges Minister Obaidul Quader on Thursday told Parliament that all-out efforts are on the construction works on the Padma Bridge by December 2018, reports UNB.
“Efforts are on to complete the bridge by December 2018 through installation of the remaining spans in phases alongside pile driving and installation of pair columns,” Quader said.
The minister said this while responding to a starred question from Awami League MP Salina Begum (Reserved seat-6).
He, however, said the finalisation of the design of its piles is getting delayed slightly at 14 locations due to difference in the river's soil layers.
|
Editor : M. Shamsur Rahman
Published by the Editor on behalf of Independent Publications Limited at Media Printers, 446/H, Tejgaon I/A, Dhaka-1215.
Editorial, News & Commercial Offices : Beximco Media Complex, 149-150 Tejgaon I/A, Dhaka-1208, Bangladesh. GPO Box No. 934, Dhaka-1000.
Editor : M. Shamsur Rahman
Published by the Editor on behalf of Independent Publications Limited at Media Printers, 446/H, Tejgaon I/A, Dhaka-1215.
Editorial, News & Commercial Offices : Beximco Media Complex, 149-150 Tejgaon I/A, Dhaka-1208, Bangladesh. GPO Box No. 934, Dhaka-1000.