State Minister for Power and Energy Nasrul Hamid has said a 1 MW capacity waste-to-energy power project will be implemented in Keraniganj upazila within the next 30 months to generate electricity from garbage, reports UNB.
He mentioned that if Keraniganj waste-to-energy project becomes successful, more projects will be undertaken to generate electricity from garbage in different upazilas across the country.
He made the announcement while inaugurating a 33/11 kV substation and multi-storied office building of Dhaka Palli Bidyut Samity-4 at Jheelmil-1 Housing Project in Keraniganj on Saturday.
Rural Electrification Board (REB) has installed the substation through its Dhaka Palli Bidyut Samity-4.
The State Minister also laid the foundation of different substations with similar capacity at Jheelmil-2 project, Konakhola, Chargalgalia and Washpur.
Being an MP from Keraniganj, Nasrul Hamid noted that a master plan is being adopted to develop the suburb as a modern locality.
He said it will reduce population pressure on Dhaka city if all modern amenities are ensured for people of the Keraniganj upazila.
|
The National Board of Revenue (NBR) is set to start drive in various business entities to detect foreign workers engaged in jobs here but not paying taxes, reports UNB. “A taskforce team will inspect… 
Editor : M. Shamsur Rahman
Published by the Editor on behalf of Independent Publications Limited at Media Printers, 446/H, Tejgaon I/A, Dhaka-1215.
Editorial, News & Commercial Offices : Beximco Media Complex, 149-150 Tejgaon I/A, Dhaka-1208, Bangladesh. GPO Box No. 934, Dhaka-1000.
Editor : M. Shamsur Rahman
Published by the Editor on behalf of Independent Publications Limited at Media Printers, 446/H, Tejgaon I/A, Dhaka-1215.
Editorial, News & Commercial Offices : Beximco Media Complex, 149-150 Tejgaon I/A, Dhaka-1208, Bangladesh. GPO Box No. 934, Dhaka-1000.
|